Artificial intelligence: what each party would do

What each of BC’s five parties has committed to on artificial intelligence, with BC’s regulation on electricity for A.I. data centres, the public service’s policy on generative AI and the ministry’s materials for schools.

Party sites checked October 6, 2026

Each party on artificial intelligence

BC’s rules on AI in plain words

BC’s rules on power for AI data centres

  • BC law lets cabinet regulate the electricity a public utility supplies for storing or processing electronic data, including data used for artificial intelligence. Utilities Commission Act, section 21.1
  • The regulations may stop a utility supplying power to such a facility, cap the capacity available, or require a competition for it. Section 21.1
  • A 2026 regulation defines an A.I. data centre as a data centre where 10 percent or more of the electricity is used for artificial intelligence computing, its data or the equipment for them. B.C. Reg. 8/2026, section 1
  • Over the two years from February 1, 2026 it caps new power for conventional data centres at 100 MW, and for A.I. data centres at 300 MW plus any of that 100 MW not made available. Section 3; Utilities Commission Act, RSBC 1996, c. 473
  • BC Hydro must run a competition to decide which data centres get new power, unless it finds too little demand or too little capacity, and no request may exceed 145 MW. Section 4; Utilities Commission Act, RSBC 1996, c. 473
Read the regulation at BC Laws

AI in government and schools

The policy at digital.gov.bc.ca

Power for AI data centres

Power cap for A.I. data centres New capacity over the two years from February 1, 2026, plus any conventional data centre capacity not taken up
300 MW B.C. Reg. 8/2026, section 3
Power cap for conventional data centres New capacity over the two years from February 1, 2026
100 MW B.C. Reg. 8/2026, section 3
Largest single request In BC Hydro’s competitive process
145 MW B.C. Reg. 8/2026, section 4
BC Hydro’s competitive call for A.I. and data centre projects A two-year call; projects of 10 MW and greater
Launched February 1, 2026 Industrial Electricity Allocation Framework, page last updated March 31, 2026

Recorded votes

  1. Second reading of Bill 31, Energy Statutes Amendment Act, 2025: passed, 48 to 42. The bill also amended the Hydro and Power Authority Act.

    48 for 42 against 3 did not vote

  2. Third reading of Bill 31, Energy Statutes Amendment Act, 2025: passed, 46 to 46. The vote was tied and the Speaker’s casting vote was in favour. Royal Assent November 27, 2025. The bill also amended the Hydro and Power Authority Act.

    46 for 46 against 1 did not vote

The tables

Limits on new electricity capacity BC Hydro may make available, in megawatts

PurposeTwo-year period commencing on the reference dateOne-year period commencing on its second anniversary
Conventional data centres100 MW50 MW
A.I. data centres300 MW, plus conventional capacity not made available150 MW, plus conventional capacity not made available
Hydrogen-for-export facilities200 MW100 MW

Source: Data Centre Facility and Hydrogen Production Facility Power Supply Regulation, B.C. Reg. 8/2026.

Keep comparing

Each party’s page, at artificial intelligence

Sources